Home • Projects
The Delta High School project consists of 3 phases of construction. The 1st involves an 11,600 sf (approx.) addition which will include a new Gym, Weight room and Corridor. Construction…
The Ridgway Reservoir Spillway Fish Screen project is composed of a series of concrete footings and buttresses surrounding the spillway structure of the Ridgway Reservoir. This foundation will support an…
This is the latest Maverik convenience store to be built in Western Colorado. Mays Concrete was responsible for construction of the building foundations as well as all site concrete improvements. …
The El Jebel Car Wash is the latest project by Crawford Properties, LLC and includes 3 car wash bays with a center equipment room/attendant office area. The structure is built…
Our first pour with the new concrete pump!
The Kannah Creek Intake Structure, constructed for the City of Grand Junction, included 6’ – 12’ high structure walls which divert water from Kannah Creek to the domestic water processing…
The 734 Main Street Office Building, located near downtown Grand Junction, will offer over 30,000 sf of new office space to the growing Grand Junction Business District. The Structure has…
This City of Grand Junction project includes construction of 8,000 LF of 10 Ft. wide, 6” thick concrete trail adjacent to Monument Road. More than 1,600 CY of concrete will…
The Green River Canal Fish Screen is a canal diversion structure located along the Green River in Utah. The structure, near the canal inlet, allows water to pass thru a…
This project will consist of 5,500 cy of concrete paving, over 200,000 sf. using our Bidwell machine.
This job is a Structural and Civil project, and includes construction of retaining walls, a bus stop shelter, ½ mile of mountable curb and gutter, sidewalks, and bus pullout paving. …
The Civil Division is performing this work for Mesa County as a Subcontractor to United Companies. The project includes installing 3600 LF of new bike/pedestrian trail, new drive aprons for…
This is the new 4,400 square foot main entrance plaza at Columbine Middle School in Montrose. This part of the project involved constructing six concrete seatwall sections, placing colored concrete…
This is Phase 3 of an on-going subdivision development located north of Hwy. 6 in Silt, CO. This phase of the project will consume 600+ CY of concrete, and includes…
By the time we complete this project, it will have consumed 430 CY of concrete, and have taken two different slipform machines and five different molds to complete. Our Structural…
This project includes fueling islands, fuel tank cover slabs, sidewalks, curb and gutter, as well as improvements to Wine Valley Road and Elberta Avenue in Palisade.
This project involved construction of a new overflow parking lot for the new Corner Square Building 3 and existing Corner Square Building 4. Work included curb and gutter, new driveway…
This project included construction of shooting bay shade structures, group picnic structures, restroom pads and sidewalks for the new world-class shooting range at Cameo.
The Las Colonias Business Park – Phase I & IA is a project for the City of Grand Junction. MCI’s Structural and Civil Divisions are working on the project. The…
Mays is constructing 50 ea. 36” diameter caissons (1433 lf total) supporting almost 800 lf. of 12” thick retaining wall running along the west bound exit ramp at exit 49.
Brown Ranch Phase 6 is a 29 lot subdivision located in Montrose, CO. These photos show our crews placing 8 1/2 ft. wide mountable curb, gutter and sidewalk. This is…
Over 900 LF of Slip-Formed Type 7 concrete barrier wall was installed for La Plata County. The location of the project is on La Plata County Road 120, approximately 5 miles southwest of…
45,000 SF of Sidewalk, 10,000 SF of Misc. flatwork, 4,400 LF of curb & gutter, 3,000 SF of ADA ramps, 135 detectable warning plates and 38 light pole bases.
Gang formed tall wall foundation with integral pilasters. Wall heights up to 20′ tall. 14,000 SF of interior slabs. 12,000 SF of structural topping slabs with sloped overlays.
This project includes 1190 CY of detached sidewalk, curb and gutter, median curb and median gutter.
This work included 250 CY of mountable curb, gutter and sidewalk, crosspans & fillets, and tract sidewalks.
3 stair/elevator cores built simultaneously. Structural foundations of pile caps and grade beams. 150,000 SF of interior flat work and deck pours.
ACI Rocky Mountain Project of the Year Award Winner The Montrose Rec Center earned the above award from the ACI for the following: 47,000 SF of insulated and architectural tilt-up…